Given Year 0 1 2 3 4 Project A $-350 $50 $100 $150 $200 Project B $-250 $125 $100 $75 $50 Hurdle rate = 10%,

  1. Given

Year

0

1

2

3

4

Project A

$-350

$50

$100

$150

$200

Project B

$-250

$125

$100

$75

$50

Hurdle rate = 10%,

Use incremental IRR analysis to decide whether you should take project A instead of project B.