Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available: Quantity of direct labor used

Glacier Bicycle Company manufactures commuter bicycles from recycled materials. The following data for October of the current year are available:

Quantity of direct labor used 540 hrs.
Actual rate for direct labor $14.20 per hr.
Bicycles completed in October 250 bicycles
Standard direct labor per bicycle 2 hrs.
Standard rate for direct labor $14.50 per hr.

a. Determine for October the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct Labor Rate Variance $
Direct Labor Time Variance $
Total Direct Labor Cost Variance $

b. How much direct labor should be debited to Work in Process? $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ACCA Advanced Audit And Assurance

Authors: Nick Blackwell, Annabel Lefton, Emile Woolf International

1st Edition

1848434715, 978-1848434714

More Books

Students also viewed these Accounting questions

Question

What problems do you see here, especially as it relates to control?

Answered: 1 week ago

Question

How We Listen?

Answered: 1 week ago