Good luck! D Question 24 Which of the following is true for the CPM/PERT technique? O It is applicable at all stages of a project
Good luck! D Question 24 Which of the following is true for the CPM/PERT technique? O It is applicable at all stages of a project life cycle. O Project activity time is objectively assessed by CPM/PERT. O It considers the possibility that some activities may fail. O There is the inherent danger of placing too much emphasis on slack activities, Previous 1 pts Next No new data to save. Last checked at 4:14pm Submit