Question
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products: Activity Cost Pool Activity Rate Setting up batches
Gould Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products:
Activity Cost Pool | Activity Rate | ||||||||||
Setting up batches | $ | 59.41 | per batch | ||||||||
Processing customer orders | $ | 72.87 | per customer order | ||||||||
Assembling products | $ | 4.10 | per assembly hour | ||||||||
Data concerning two products appear below:
Product K91B | Product F65O | |
Number of batches | 86 | 57 |
Number of customer orders | 36 | 50 |
Number of assembly hours | 490 | 897 |
How much overhead cost would be assigned to Product K91B using the activity-based costing system? (Round your intermediate calculations and final answers to 2 decimal places.)
.
Paparo Corporation has provided the following data from its activity-based costing system:
Activity Cost Pool | Total Cost | Total Activity | |||||||
Assembly | $ | 869,200 | 53,000 | machine-hours | |||||
Processing orders | $ | 56,700 | 1,500 | orders | |||||
Inspection | $ | 100,681 | 1,330 | inspection-hours | |||||
Data concerning the company's product Q79Y appear below:
Annual unit production and sales | 550 | ||||||||
Annual machine-hours | 1,030 | ||||||||
Annual number of orders | 65 | ||||||||
Annual inspection hours | 40 | ||||||||
Direct materials cost | $ | 48.00 | per unit | ||||||
Direct labor cost | $ | 41.11 | per unit | ||||||
According to the activity-based costing system, the average cost of product Q79Y is closest to:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started