Green Grass's plant manager just received marketing's latest forecasts of Big Broadcaster sales for the next year. Given that, Cycle time: 52 seconds/unit Theoretical minimum
Green Grass's plant manager just received marketing's latest forecasts of Big Broadcaster sales for the next year. Given that, Cycle time: 52 seconds/unit Theoretical minimum for the number of stations: 14 The Sum of work element times: 700 seconds What would be the line's efficiency? Group of answer choices 90.4 81.3 96.15 88.5 99.5