Gulf Coast Electronics is ready to award contracts to suppliers for providing reservoir capacitors for use in its electronic devices. For the past several years,

Gulf Coast Electronics is ready to award contracts to suppliers for providing reservoir capacitors for use in its electronic devices. For the past several years, Gulf Coast Electronics has relied on two suppliers for its reservoir capacitors: Able Controls and Lyshenko Industries. A new firm, Boston Components, has inquired into the possibility of providing a portion of the reservoir capacitors needed by Gulf Coast.
The quality of products provided by Lyshenko Industries has been extremely high; in fact, only 0.5% of the capacitors provided by Lyshenko had to be discarded because of quality problems. Able Controls has also had a high quality level historically, producing an average of only 1% unacceptable capacitors. Because Gulf Coast Electronics has had no experience with Boston Components, it estimated Boston Components' defective rate to be 10%.
Gulf Coast would like to determine how many reservoir capacitors should be ordered from each firm to obtain 75,000 acceptable-quality capacitors to use in its electronic devices. To ensure that Boston Components will receive some of the contract, management specified that the volume of reservoir capacitors awarded to Boston Components must be at least 10% of the volume given to Able Controls.
In addition, the total volume assigned to Boston Components, Able Controls, and Lyshenko Industries should not exceed 30,000,50,000, and 50,000 capacitors, respectively. Because of Gulf Coast's long-term relationship with Lyshenko Industries, management also specified that at least 30,000 capacitors should be ordered from Lyshenko.
The cost per capacitor is $2.45 for Boston Components, $2.50 for Able Controls, and $2.75 for Lyshenko Industries.
(a)
Formulate a linear program for determining how many reservoir capacitors should be ordered from each supplier to minimize the total cost of obtaining 75,000 acceptable-quality reservoir capacitors. (Let B = number of capacitors ordered from Boston Components, A = number of capacitors ordered from Able Controls, and L = number of capacitors ordered from Lyshenko Industries.)
Min
Correct: Your answer is correct.
s.t.
volume for Boston
volume for Able
volume for Lyshenko
# useful capacitors
Incorrect: Your answer is incorrect.
Boston relative to Able
Lyshenko minimum
B, A, L >=0
Solve the linear program to determine how many reservoir capacitors should be ordered from each supplier. (Round your answers to the nearest integer.)
Boston Components
capacitors
Able Controls
50000
Incorrect: Your answer is incorrect.
capacitors
Lyshenko Industries
capacitors
(b)
Suppose that the quality level for reservoir capacitors supplied by Boston Components is much better than estimated, with a defective rate of 2%. What effect, if any, would this quality level have?
The optimal solution would change, with 30,000 reservoir capacitors assigned to Boston Components.
The optimal solution would change, with Lyshenko Industries being assigned the maximum of 50,000 reservoir capacitors.
The optimal solution would change, with 7,526 reservoir capacitors assigned to Boston Components.
The optimal solution would remain the same.
Correct: Your answer is correct.
(c)
Suppose that management is willing to reconsider their requirement that at least 30,000 capacitors must be ordered from Lyshenko Industries. What effect, if any, would this consideration have on the solution in part (a)?
The total cost will decrease about $2.54 for every unit the required minimum is reduced by, with no lower limit on how much the required minimum can be reduced.
The total cost will decrease about $0.22 for every unit the required minimum is reduced by, for at least 21,106 capacitors.
The total cost will decrease about $0.16 for every unit the required minimum is reduced by, for at least 25,440 capacitors
Reducing the requirement will not change the total cost of obtaining the reservoir capacitors.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions