GWUs football stadium has seven sections: East, West, North lower section, North upper section, South lower section, South upper section, and Luxury Club section.The attendance
GWUs football stadium has seven sections: East, West, North lower section, North upper section, South lower section, South upper section, and Luxury Club section.The attendance data for each section since 2000 is available. Any combination of sections can be selected for expansion, the GWU administrators want to increase capacity of only two sections due to complexity of the project, limitations of budget, and time constraints. To select the two sections for expansion, attendance data for each section can be used. The attendance data is available for potential contractors.
Time Estimates (days) | ||||||
Description | Activity | Predecessor(s) | Optimistic | Most Likely | Pessimistic | Crash cost/day |
Bonding, insurance, tax structuring | A | - | 20 | 30 | 40 | $1.500 |
Removing current structure(s) | B | A | 20 | 65 | 80 | $3.500 |
Foundation, concrete footings | C | A | 50 | 60 | 100 | $4.000 |
Upgrading walkways, stairwells, elevators | D | C | 30 | 50 | 100 | $1.900 |
Interior wiring | E | B | 25 | 30 | 35 | $9.500 |
Inspection approvals | F | E | 0,1 | 0,1 | 0,1 | $0 |
Plumbing | G | D,F | 25 | 30 | 35 | $2.500 |
Painting | H | G | 10 | 20 | 30 | $2.000 |
Hardware/ AC/ Metal workings | I | H | 20 | 25 | 60 | $2.000 |
Installing Seats | J | H | 8 | 10 | 12 | $6.000 |
Inspection | K | J | 0,1 | 0,1 | 0,1 | $0 |
Final detail work/ cleanup | L | I,K | 20 | 25 | 60 | $4.500 |
Assume that you have identified the major activities that must be done to complete the project are as follows.
-Bonding, insurance, tax structuring
-Removing current structure(s)
-Foundation, concrete footings
-Upgrading walkways, stairwells, elevators
-Interior wiring
-Inspection approvals
-Plumbing
-Painting
-Hardware/ AC/ Metal workings
-Installing Seats
-Inspection
-Final detail work/ cleanup
According to the informations above
a)Develop a network drawing for the expansion project.
b)Identify critical path(s) and calculate expected finish time.
c)Calculate the probability of finishing the project in 270 days.
d)create a project proposal. It should include WBS, resource requirements, project schedule, budget plan (timed). Also, include risks and mitigation strategies.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started