Habitat for Humanity International is a nonprofit organization dedicated to eliminating poverty housing worldwide. Suppose the following table contains estimates of activity times (in days)

Habitat for Humanity International is a nonprofit organization dedicated to eliminating poverty housing worldwide. Suppose the following table contains estimates of activity times (in days) involved in the construction of a house that Habitat for Humanity is building.

ActivityOptimisticMost ProbablePessimistic
A56.07
B89.010
C66.510.5
D68.09
E56.08
F45.06

(a)

Compute the expected activity completion times and the variance for each activity. (Round your answers to two decimal places.)

ActivityExpected
Times
Variance
A
B
C
D
E
F

(b)

An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. (Round your answers to two decimal places.) expected project completion time- variance of projection completion time-

Step by Step Solution

3.39 Rating (146 Votes )

There are 3 Steps involved in it

Step: 1

Let optimistic time be denoted by a Let most probable time be denoted by m Let pessimistic ti... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Gerard Cachon, Christian Terwiesch

2nd International Edition

1260547612, 978-1260547610

More Books

Students also viewed these Accounting questions

Question

How do people develop skills?

Answered: 1 week ago

Question

Express the following ratios in its lowest terms.

Answered: 1 week ago