Habitat for Humanity International is a nonprofit organization dedicated to eliminating poverty housing worldwide. Suppose the following table contains estimates of activity times (in days)
Habitat for Humanity International is a nonprofit organization dedicated to eliminating poverty housing worldwide. Suppose the following table contains estimates of activity times (in days) involved in the construction of a house that Habitat for Humanity is building.
Activity | Optimistic | Most Probable | Pessimistic |
---|---|---|---|
A | 5 | 6.0 | 7 |
B | 8 | 9.0 | 10 |
C | 6 | 6.5 | 10.5 |
D | 6 | 8.0 | 9 |
E | 5 | 6.0 | 8 |
F | 4 | 5.0 | 6 |
(a)
Compute the expected activity completion times and the variance for each activity. (Round your answers to two decimal places.)
Activity | Expected Times | Variance |
---|---|---|
A | ||
B | ||
C | ||
D | ||
E | ||
F |
(b)
An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. (Round your answers to two decimal places.) expected project completion time- variance of projection completion time-
Step by Step Solution
3.39 Rating (146 Votes )
There are 3 Steps involved in it
Step: 1
Let optimistic time be denoted by a Let most probable time be denoted by m Let pessimistic ti...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started