Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of $4,000,000. The contract is to start in July

Hardhat Construction Company has a contract to construct a $4,500,000 bridge at an estimated cost of $4,000,000. The contract is to start in July 2014, and the bridge is to be completed in October 2016. The following data pertain to the construction period. 2014 2015 2016 Costs to date $4,050,000 Estimated costs to complete Progress billings during the year Cash collected during the year $1,000,000 3,000,000 900,000 750,000 $2,916,000 1,134,000 2,400,000 1,750,000 1,200,000 2,000,000 Record the journal entries for 2014, 2015, and 2016 using the percentage of completion method Record the income statement and balance sheet for 2014, 2015, and 2016

Step by Step Solution

3.53 Rating (163 Votes )

There are 3 Steps involved in it

Step: 1

Contract price 4500000 4500000 4500000 Less estimated cost 100... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray H. Garrison, Eric W. Noreen, Peter C. Brewer

13th Edition

978-0073379616, 73379611, 978-0697789938

More Books

Students also viewed these Accounting questions

Question

What is meant by relative profitability?

Answered: 1 week ago

Question

What payments are included in the lease liability?

Answered: 1 week ago