Question

1 Approved Answer

he will reduce his component lot sizes. He has developed the following data for one component, the safety chain clip: Setup labor cost $ 3

he will reduce his component lot sizes. He has developed the following data for one component, the safety chain clip:
Setup labor cost $30 per hour
Annual holding cost $15 per unit
Daily production ,1,008 units/8 hour day
Annual demand ,24,840(270 days each daily demand of 92 units)
Desired lot size 126 units (one hour of production)
To obtain the desired lot size, the set-up time that should be achieved =, minutes (round your response to two decimal places).
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management In The Supply Chain Decisions And Cases

Authors: Roger Schroeder, Susan Goldstein

8th Edition

1260368106, 9781260368109

More Books

Students also viewed these General Management questions

Question

What is meant by managing paradox and contradiction?

Answered: 1 week ago

Question

Discuss the problems associated with establishing corporate image.

Answered: 1 week ago