Headway company has a budget of BD250,000 which can be allocated for new projects. There are four (4) proposals which are being considered and presented
Headway company has a budget of BD250,000 which can be allocated for new projects. There are four (4) proposals which are being considered and presented in the table below. If MARR is 25%, which of the project/s shall be prioritized? Project Number IRR (%) Project Cost 1 28.75% BD150,000 2 22.50% BD75,000 3 25.00% BD100,000 4 18.25% BD50,000