Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week

Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week

8.

Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering.

Item

Lead Time

On-Hand Inventory

Components

Stepper

2

20

A(2),

B(2),

C(2)

A

1

10

D(1),

F(2)

B

2

20

E(2),

F(3)

C

2

10

D(2),

E(1)

D

1

15

E

2

5

F

2

20

c) Develop a net material requirements plan for F (enter your responses as whole numbers).

Week

Lead Time

Item

1

2

3

4

5

6

7

8

(weeks)

F

Gross req

2

On hand

Net req

enter your response here

enter your response here

Order receipt

enter your response here

enter your response here

Order release

enter your response here

enter your response here

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistical Techniques in Business and Economics

Authors: Douglas A. Lind, William G Marchal

17th edition

1259666360, 978-1259666360

More Books

Students also viewed these Mathematics questions