Question
Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week
Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week
8.
Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering.
Item | Lead Time | On-Hand Inventory | Components |
Stepper | 2 | 20 | A(2), B(2), C(2) |
A | 1 | 10 | D(1), F(2) |
B | 2 | 20 | E(2), F(3) |
C | 2 | 10 | D(2), E(1) |
D | 1 | 15 | |
E | 2 | 5 | |
F | 2 | 20 |
c) Develop a net material requirements plan for F (enter your responses as whole numbers).
Week | Lead Time | ||||||||||
Item | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | (weeks) | ||
F | Gross req | 2 | |||||||||
On hand | |||||||||||
Net req | enter your response here | enter your response here | |||||||||
Order receipt | enter your response here | enter your response here | |||||||||
Order release | enter your response here | enter your response here |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3