Hector Company purchased land for an office site by paying $900,000 cash on January 1, 2019. Hector began construction on the office building on January
Hector Company purchased land for an office site by paying $900,000 cash on January 1, 2019. Hector began construction on the office building on January 1 and finished December 31, 2019. The following expenditures were incurred for construction
Date | Expenditures |
January 1, 2019 | $600,000 |
April 1, 2019 | $840,000 |
October 1, 2019 | $1,500,000 |
December 1, 2019 | $2,400,000 |
Calculate the weighted-average accumulated expenditure on the project during the year 2019 was:
a. $1,735,000
b. $1,805,000
c. $1,880,000
d. $1,800,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started