Helix Company produces several products in its factory, including a karate robe. The company uses a standard cost system to assist in the control of

Helix Company produces several products in its factory, including a karate robe. The company uses a standard cost system to assist in the control of costs. According to the standards that have been set for the robes, the factory should work 780 direct labor-hours each month and produce 7,800 robes. The standard costs associated with this level of production are as follows:

Total Per Unit of Product
Direct materials $ 167,232 $ 21.44
Direct labor $ 23,400 3.00

Variable manufacturing overhead (based on direct labor-hours)

$ 1,560 0.20

$ 24.64

During April, the factory worked only 740 direct labor-hours and produced 7,900 robes. The following actual costs were recorded during the month:

Total Per Unit of Product
Direct materials (26,070 yards) $ 156,420 $ 19.80
Direct labor $ 25,280 3.20

Variable manufacturing overhead

$ 14,220 1.80
$ 24.80

At standard, each robe should require 3.2 yards of material. All of the materials purchased during the month were used in production.

Required:
1.

Compute the materials price and quantity variances for April: (Input all amounts as positive values. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.)

Materials price variance $ (Click to select)NoneUF
Materials quantity variance $ (Click to select)UFNone

2.

Compute the labor rate and efficiency variances for April: (Input all amounts as positive values. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Do not round your intermediate calculations. Round your final answers to the nearest dollar.)

Labor rate variance $ (Click to select)FUNone
Labor efficiency variance $ (Click to select)UNoneF

3.

Compute the variable manufacturing overhead rate and efficiency variances for April: (Input all amounts as positive values. Leave no cells blank - be certain to enter "0" wherever required. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.)

Variable overhead rate variance $ (Click to select)FNoneU
Variable overhead efficiency variance $ (Click to select)UFNone

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions