Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Hello, can you complete this? I really liked your work on the other questions you answered yesterday. It is late notice, but I need this

Hello, can you complete this? I really liked your work on the other questions you answered yesterday. It is late notice, but I need this by 2pm on 1/15/2017. If you are not able to complete it, please let me know. Thank you.

QUESTION 1

What is the Internal Rate of Return (IRR) for the following cash flows?

Year

CFs

0

-1,000

1

100

2

200

3

350

4

800

Enter your answer rounded off to two decimal points. Do not enter % in the answer box. For example, if your answer is 0.12345 then enter as 12.35 in the answer box.

QUESTION 2

What is the net present value of a project with the following cash flows if the discount rate is 12 percent?

Year

CFs

0

-1,210

1

431

2

272

3

232

4

341

Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. For example, if your answer is $12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 3

Which one of the following methods of analysis ignores the time value of money?

Net present value

Modified Internal rate of return

Payback

Internal rate of return

Profitability index

1 points

QUESTION 4

Which of the following is the correct definition of Internal Rate of Return (IRR)?

IRR is the rate at which Net Present Value (NPV) equals initial outlay.

IRR is the rate at which the Net Present Value (NPV) equals present value of all future cash flows.

IRR is the rate of return required by project's investors.

IRR is the rate at which the present value of all future cash flows equals initial outlay.

IRR is the same as Average Accounting Rate of Return.

1 points

QUESTION 5

What is the profitability index of a project with the following cash flows if the discount rate is 17 percent?

Year

CFs

0

-1,277

1

725

2

456

3

338

Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 6

A project has the following cash flows. What is the payback period?

Year

CFs

0

-$235

1

$66

2

$58

3

$46

4

$255

Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 7

What is the Modified Internal Rate of Return (MIRR) for the following cash flows? Assume that the required rate of return is 4%

Year

CFs

0

-1,000

1

100

2

200

3

350

4

800

Enter your answer rounded off to two decimal points. Do not enter % in the answer box. For example, if your answer is 0.12345 then enter as 12.35 in the answer box.

1 points

QUESTION 8

A project has the following cash flows. What is the payback period?

Year

CFs

0

-$436

1

$290

2

$55

3

$201

4

$87

Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 9

Which one of the following indicates that a project is expected to create value for its owners?

Profitability index less than zero

Payback period greater than the cut-off period

Internal rate of return (IRR) that is less than the required rate of return

NPV that is greater than zero

Positive IRR

1 points

QUESTION 10

What is the net present value of a project with the following cash flows if the discount rate is 18 percent?

Year

CFs

0

-509

1

207

2

337

3

322

4

393

Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. For example, if your answer is $12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 11

ABC Inc. is considering a project with an initial cost of $1,580. The project will not produce any cash flows for the first four years.Starting in year five, the project will produce cash inflows of $844 a year for four years. If the discount rate of 3 percent, what is the project's net present value?

Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. For example, if your answer is$12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 12

What is the profitability index of a project with the following cash flows if the discount rate is 15 percent?

Year

CFs

0

-1,445

1

299

2

236

3

302

4

560

Enter your answer rounded off to two decimal points. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 13

Suppose a project has initial outlay of $12,000 and after-tax cash flows of $2,000 each year for first three years and $4,000 eachyear for the following three years. If the required rate of return is 6.50%, what is the equivalent annual annuity?

Enter your answer rounded off to two decimal points.

1 points

QUESTION 14

What is the net present value of a project with the following cash flows if the discount rate is 16 percent?

Year

CFs

0

-811

1

972

2

389

3

299

Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. For example, if your answer is $12.345 then enter as 12.35 in the answer box.

1 points

QUESTION 15

What is the profitability index of a project with the following cash flows if the discount rate is 11 percent?

Year

CFs

0

-255

1

204

2

251

3

226

4

319

Enter your answer rounded off to two decimal points. For example, if your answer is 12.345 then enter as 12.35 in the answer box.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Investment Analysis and Portfolio Management

Authors: Frank K. Reilly, Keith C. Brown, Sanford J. Leeds

11th Edition

1305262999, 1305262997, 035726164X, 978-1305262997

More Books

Students also viewed these Finance questions