Hello! Can you help? A project is expected to provide cash flows of $11,550, $12,200, $15,300, and $9,800 over the next four years, respectively. At
Hello!
Can you help?
A project is expected to provide cash flows of $11,550, $12,200, $15,300, and $9,800 over the next four years, respectively. At a required return of 9.6 percent, the project has a profitability index of .717. For this to be true, what is the project's cost at Time 0?