Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Hello Everyone! I would really like help with this question. Thank you in advance! A project's NPV profile graph intersects the Y-axis at 0% cost

Hello Everyone! I would really like help with this question. Thank you in advance!

image text in transcribed

A project's NPV profile graph intersects the Y-axis at 0% cost of capital and intersects the X-axis at the project's -Select- (where NPV = 0). The Y-axis intersection point represents the project's undiscounted NPV. The point at which 2 projects' profiles cross one another is the crossover rate. The crossover rate can be found by calculating the - Select of the differences in the projects' cash flows (Project Delta). A -Select- NPV profile indicates that increases in the cost of capital lead to large declines in NPV. If a project has most of its cash flows coming in later years, its NPV will -Select- sharply if the cost of capital increases; but a project whose cash flows come earlier will not be severely penalized by high capital costs. The significance of the crossover rate is that at any cost of capital -Select-than the crossover rate, the NPV and IRR methods will provide the same conclusion for evaluating mutually exclusive projects. However, at any cost of capital -Select-than the crossover rate, the NPV and IRR methods' conclusions will conflict. In that situation, the -Select- v method will always provide the correct project acceptance result. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 8%. 1 2 3 700 215 Project A Project B -1,500 -1,500 370 310 310 755 300 395 What Project Delta's IRR? Do not round intermediate calculations. Round your answer to two decimal places. % What is the significance of this IRR? It is the -Select- V after this point when mutually exclusive projects are considered there is no conflict in project acceptance between the NPV and IRR approaches. Review the graphs below. Select the graph that correctly represents the correct NPV profile for Projects A and B by using the following drop down menu. -Select- NPV Profiles A NPV Profiles B NPV Profiles c NPV Profiles D NPV (5) 600+ 500+ 400 300 200+ 100 NPV (5) 600 5001 400 300 200+ NPV (5) 6001 5001 400+ 300 2001 100 INPV (5 6001 500 400 3001 2007 100 100 . 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 5 10 15 20 25 30 Cost of Capital %) -100 -200 Cost of Capital %) Cost of Capital% Cost of Capital (%) -1001 -2001 -300 -400+ -100 -200 -300+ -400+ -1001 -200 -3001 -4001 -300 -400+

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Derivatives Markets

Authors: Robert McDonald

3rd Edition

978-9332536746, 9789332536746

More Books

Students also viewed these Finance questions

Question

The __________ can be used to expand expressions like (2x + 3) 6 .

Answered: 1 week ago

Question

Which employees are more likely to prefer flextime?

Answered: 1 week ago