Question

1 Approved Answer

Hello, I am stuck in calculation . I managed to figure out the question one , any one can help with remaining ? Thank you

Hello,

I am stuck in calculation . I managed to figure out the question one , any one can help with remaining ?

Thank you .

Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager's table of activities are noted below.

ID Activity Original Duration (days)

Actual Duration

(days)

Actual Start Date Actual Finish Date

%

Complete

Original

Budget

Actual

Budget

10 Site Prep 8 9 2/27 4/26 100 $500,000 $600,000
20 Substructure 12 11 5/1 7/18 100 $1,500,000 $1,350,000
30 Super Substructure 18 - 7/20 - 75 $2,000,000 $1,450,000
40 Exterior 6 - - - 0 $400,000 -
50 Interior 14 - 8/31 - 50 $1,800,000 $1,000,000
60 Services 10 - - - 0 $1,000,000 -
70 Cleanup 4 - - - 0 $200,000

Question 1: Forecast the duration of the activities that are currently in progress assuming their current rate of progress will continue till the end of the project. Find out the remaining duration as per the forecasted duration.

Step 1 - Determine activities in progress (ID 30 and ID50) - Less than 100% complete

Step 2 - Calculate actual duration from activity start date to status date for each activity in progress. The remaining duration calculation must be computed using the % of work completed to date.

ID 30 - Activity 30 Super Substructure

Actual Duration up to status date = 14.2 #weeks to status date (Activity start date -7/20) thru (Project Status Date - 10/28)

% of work Complete = 75% (From Chart above)

New Duration at 100% = 100 * 14.2_ #weeks to status date / 75 (% of work complete) = _18.93_____ #weeks to complete 100%

Remaining Duration at 25% = 4.7__ weeks to complete 100% - #weeks to status date 11/30/22____

ID 50 - Activity 50 Interior

Actual Duration up to status date = ___8.2___#weeks to status date (Activity start date -8/31) thru (Project Status Date - 10/28)

% of work Complete = 50% (From Chart above)

New Duration at 100% = 100 * __8.2___#weeks to status date / 50 (% of work complete) = ___16.4___ #weeks to complete 100%

Remaining Duration at 50% = __8.2___#weeks to complete 100% - #weeks to status date __12/25/22_________

Question 2: Calculate the Planned Value (BCWS) based on the original budget, the original duration, and the number of weeks between the planned early start date and the status date (October 28th for the activities that are in progress. This calculation will provide the amount of money the project has spent up to October 28th?

Activity 30 - Super substructure

Original Budget = $2,000,000

Original Duration = 18 Weeks

Number of Weeks between Planned Start Date and Status State = ______ #Weeks to status date (From Question 1.

BCWS = #Weeks to status date / Original Duration * Original Budget

BCWS = ______________________________

Activity 50 - Interior

Original Budget = $1,800,000

Original Duration = 14 Weeks

Number of Weeks between Planned Start Date and Status State =_______ #Weeks to status date (From Question 1).

BCWS = #Weeks to status date / Original Duration * Original Budget

BCWS = ______________________________

Question 3 - Calculate the BCWP (Earned Value). This is based on the original budget and the actual work completed for the activities that are in progress. This calculation will provide the budgeted cost of the work completed to date.

Activity 30: Super Sub Structure

Original Budget: = $2,000,000

Actual Percent Complete = 75%

Earned Value = 75% * Original Budget _____________________

Activity 50: Interior

Original Budget = $1,800,000

Actual Percent Complete = 50%

Earned Value = 50% * Original Budget ______________________

Question 4 - Calculate the Schedule Performance Index (SPI) and the Cost Performance Index (CPI) based on BCWS and BCWP. Based on these calculations, determine if the project is ahead or behind schedule and if the cost is under or over budget?

SPI = BCWP / BCWS

CPI = BCWP / ACWP

Activity 30 = Super Substructure

SPI = _____________________

CPI = _____________________

Ahead or Behind Schedule? _____________________

Under or Over Budget? _____________________

Activity 50 = Interior

SPI = _____________________

CPI = _____________________

Ahead or Behind Schedule? _____________________

Under or Over Budget? _____________________

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions

Question

=+ 4. How can policymakers infl uence a nations saving rate?

Answered: 1 week ago