help please A project requires at least 36 worker-days to complete the project. What is the shortest time estimate for completion if the project is
help please
A project requires at least 36 worker-days to complete the project. What is the shortest time estimate for completion if the project is constrained to 3 workers per day? Assume no task requires more than one worker and the tasks can be completed independent of each other. If the answer has a fraction, round up to the closest whole number. Your Step by Step Solution