help !! The following information concerns a new project your company is undertaking. Duration (days) Predecessor Activity A 2 B 4 3 A D 1
help !!
The following information concerns a new project your company is undertaking. Duration (days) Predecessor Activity A 2 B 4 3 A D 1 E 1 B CD DE F 3 G 2 F H 3 E 1 4 H 2. GI Draw the network diagram for this project? Then determine the critical path for the project and the project completion time? - Paragraph BIEStep by Step Solution