Here are the expected cash flows for three projects: Cash Flows (dollars) Project Year: 0 1 2 3 4 A 5,100 + 1,025 + 1,025

Here are the expected cash flows for three projects:

Cash Flows (dollars)

Project Year: 0 1 2 3 4
A 5,100 + 1,025 + 1,025 + 3,050 0
B 1,100 0 + 1,100 + 2,050 + 3,050
C 5,100 + 1,025 + 1,025 + 3,050 + 5,050

a. What is the payback period on each of the projects?

Project Payback period
A years
B years
C years

b. If you use a cutoff period of 2 years, which projects would you accept?
Project A
Project B
Project C
Project A and Project B
Project B and Project C
Project A and Project C
Projects A, B, and C
None

c. If you use a cutoff period of 3 years, which projects would you accept?
Project A
Project B
Project C
Project A and Project B
Project B and Project C
Project A and Project C
Projects A, B, and C
None

d-1.

If the opportunity cost of capital is 11%, calculate the NPV for projects A, B, and C. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to 2 decimal places.)

Project NPV
A $
B $
C $

d-2. Which projects have positive NPVs?
Project A
Project B
Project C
Project A and Project B
Project B and Project C
Project A and Project C
Projects A, B, and C
None

e. "Payback gives too much weight to cash flows that occur after the cutoff date." True or false?
True
False

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions