Question
Here is a problem I had before. I also pasted the answer I havebelow. I would like if someone could please explain where are the
Here is a problem I had before. I also pasted the answer I havebelow. I would like if someone could please explain where are the numbers coming from on the answer below. I have highlighted in green the area I don't understand. Thanks!
PROBLEM:
Kitchen Kings Singapore plant manufactures three product lines, all multi-burner ceramic
cooktops. The plants three product models are the Regular (REG), the Advanced (ADV)
and the Gourmet (GMT). Until recently, the plant used a job costing system, with
manufacturing overhead applied on the basis of direct labour hours. The following table
displays the basic data upon which the conventional costing system was based.
Planned annual production | REG | ADV | GMT |
Volume in units | 5000 | 4000 | 1000 |
Production runs | 40 runs of 125 units | 40 runs of 100 units | 20 runs of 50 units |
Direct material | $129 | $151 | $203 |
Direct labour (not including setup) | $171 (9 hrs @ $19 per hr) | $209 (11 hrs @ $19 per hr) | $247 (13 hrs @ $19 per hr) |
Machine hours (MH) per product unit | 10 MH | 12 MH | 17 MH |
Total machine hours consumed by product line in a year | 50 000 (10 MH 5000) | 48 000 (12 MH 4000) | 17 000 (17 MH 1000) |
The annual budgeted overhead is $1 224 000 and the companys predetermined
overhead rate is $12 per direct labour hour. The product costs for the three product
models, as reported under the plants traditional costing system, are shown in the
following table:
REG | ADV | GMT | |
Direct material | $129 | $151 | $203 |
Direct labour (not including setup time) | $171 | $209 | $247 |
Manufacturing overhead | $108 (9 hrs @ $12 per hr) | $132 (11 hrs @ $12 per hr) | $156 (13 hrs @ $12 per hr) |
Total | $408 | $492 | $606 |
Kitchen Kings pricing policy is to set a target price for each product equal to 130 per
cent of the full product cost. Due to price competition from other appliance manufacturers,
REG units were selling at $525 and ADV units were selling for $628. These prices were
somewhat below the firms target prices. However, these results were partially offset by
great-than-expected profits on the GMT product line. Management had raised the price on
the GMT model to $800 which was higher than the original target price. Even at this price,
Kitchen Kings customers did not seem to hesitate to place orders. Moreover, the
companys competitors did not mount a challenge in the market for the GMT product line.
Nevertheless, concern continued to mount in Singapore about the difficulty in the REG and
ADV markets. After all, these were the plants bread-and-butter products, with projected
annual sales of 5000 REG units and 4000 ADV units.
Kitchen Kings director of cost management, Angela Hui, had been thinking for some
time about a refinement in the Singapore plants product costing system. Hui wondered if
the conventional volume-based system was providing management with accurate data
about product costs. She had read about activity-based costing and wondered if ABC
would be an improvement to the plants product costing system. After some discussion, an
ABC proposal was made to the companys top management and approval was obtained.
The data collected for the new ABC system is displayed in the following table.
Activity | Activity cost | Activity driver | Product line | Quantity of activity driver |
Machine related | $310 500 | Machine hours | REG ADV GMT Total | 50 000 48 000 17 000 115 000 |
Material handling | 52.500 | Production runs | REG ADV GMT Total | 40 40 20 100 |
Purchasing | 75 000 | Purchase orders | REG ADV GMT Total | 1.0 96 104 300 |
Setup | 85 000 | Production runs | REG ADV GMT Total | 40 40 20 100 |
Inspection | 27.500 | Inspection hours | REG ADV GMT Total | 4.0 4.0 300 1 100 |
Shipping | 66 000 | Shipments | REG ADV GMT Total | 5.0 4.0 200 1 100 |
Engineering | 32.500 | Engineering hours | REG ADV GMT Total | 250 2.0 200 650 |
Facility | 575 000 | Machine hours | REG ADV GMT Total | 50 000 48 000 17 000 115 000 |
Required:
1. Prepare a table similar to Exhibits which estimates the new product cost for each product line under ABC.
SOLUTION:
Calculation of new product costs under ABC:
REG | ADV | GMT | |
Direct material | $129.00 | $151.00 | $203.00 |
Direct labour (not including set up time) | 171.00 (9 hr. @ $19) | 209.00 (11 hr. @ $19) | 247.00 (13 hr. @ $19) |
Total direct costs per unit | $300.00 | $360.00 | $450.00 |
Manufacturing overhead (based on ABC)*: | |||
Machine-related | $ 27.00 | $ 32.40 | $ 45.90 |
Setup | 4.20 | 5.25 | 10.50 |
Purchasing | 5.00 | 6.00 | 26.00 |
Material handling | 6.80 | 8.50 | 17.00 |
Quality assurance | 2.00 | 2.50 | 7.50 |
Packing/shipping | 6.00 | 6.00 | 12.00 |
Engineering design | 2.50 | 2.50 | 10.00 |
Facility | 50.00 | 60.00 | 85.00 |
Total ABC overhead cost per unit | $103.50 | $123.15 | $213.90 |
Total product cost per unit | $403.50 | $483.15 | $663.90 |
* calculation of overhead costs per product
Activity | Pool rate | Product line | Activity driver quantity for product | Activity cost for product | Product line Prod. volume | Activity cost per unit of product |
Machine | $ 2.70 | REG | 50 000 | $135 000 | 5000 | $27.00 |
Related | ADV | 48 000 | 129 600 | 4000 | 32.40 | |
GMT | 17 000 | 45 900 | 1000 | 45.90 | ||
Total | 115 000 | $310 500 | ||||
Material | 525.00 | REG | 40 | $ 21 000 | 5000 | 4.20 |
Hand. | ADV | 40 | 21 000 | 4000 | 5.25 | |
GMT | 20 | 10 500 | 1000 | 10.50 | ||
Total | 100 | $ 52 500 | ||||
Purch. | 250.00 | REG | 100 | $ 25 000 | 5000 | 5.00 |
ADV | 96 | 24 000 | 4000 | 6.00 | ||
GMT | 104 | 26 000 | 1000 | 26.00 | ||
Total | 300 | $ 75 000 | ||||
Setup | 850.00 | REG | 40 | $ 34 000 | 5000 | 6.80 |
ADV | 40 | 34 000 | 4000 | 8.50 | ||
GMT | 20 | 17 000 | 1000 | 17.00 | ||
Total | 100 | $ 85 000 | ||||
Inspect. | 25.00 | REG | 400 | $ 10 000 | 5000 | 2.00 |
ADV | 400 | 10 000 | 4000 | 2.50 | ||
GMT | 300 | 7 500 | 1000 | 7.50 | ||
Total | 1100 | $ 27 500 | ||||
Ship. | 60.00 | REG | 500 | $ 30 000 | 5000 | 6.00 |
ADV | 400 | 24 000 | 4000 | 6.00 | ||
GMT | 200 | 12 000 | 1000 | 12.00 | ||
Total | 1100 | $ 66 000 | ||||
Eng. | 50.00 | REG | 250 | $ 12 500 | 5000 | 2.50 |
ADV | 200 | 10 000 | 4000 | 2.50 | ||
GMT | 200 | 10 000 | 1000 | 10.00 | ||
Total | 650 | $ 32 500 | ||||
Fac. | 5.00 | REG | 50 000 | $250 000 | 5000 | 50.00 |
ADV | 48 000 | 240 000 | 4000 | 60.00 | ||
GMT | 17 000 | 85 000 | 1000 | 85.00 | ||
Total | 115 000 | $575 000 | ||||
Grand total | $1 224 000 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started