Hi can I know only What will be the project make span if activity D is reduced by 2 days (ie from 8 to 6

Hi

can I know only

What will be the project make span if activity D is reduced by 2 days (ie from 8 to 6 days).

Activity

Dependent on

Days

A

-

2

=============

B

A

4

============

C

A

6

============

D

B,C

8

==========

E

B

3

===========

F

C

3

===========

G

D,E,F

2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions

Question

What is the purpose of the Monitoring Board?

Answered: 1 week ago