Hi I need help with a paper for this assignment. It must be able to pass an anti-plagiarism tool. McGee Carpet and Trim installs carpets

Hi I need help with a paper for this assignment. It must be able to pass an anti-plagiarism tool.

McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:

  • Activity 1: Measure office room dimensions
  • Activity 2: Estimate cost
  • Activity 3: Material requisition
  • Activity 4: Workforce requisition
  • Activity 5: Special tool requisition
  • Activity 6: Installation
  • Activity 7: Inspection and customer acceptance

Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:

Activities

OT

MT

PT

Activity 1

4

6

14

Activity 2

5

12

16

Activity 3

7

15

23

Activity 4

13

16

28

Activity 5

17

20

35

Activity 6

20

32

50

Activity 7

5

6

13

You must also do the following:

  • Determine the expected completion time and the variance for each activity
  • Determine the total project completion time and the critical path for the project
  • Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
  • What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
  • Define project management and the necessary requirements.
  • Analyze implications of changes in project scheduling.
  • Evaluate application of project management techniques in terms of the firm's business operational goals and requirements.

Please submit your assignment in an APA-formatted paper.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions

Question

Ron Franklin do you remember him? will be in town Monday.

Answered: 1 week ago

Question

Only two sites maybe three offer the things we need.

Answered: 1 week ago