Question

1 Approved Answer

Hickory Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct

Hickory Company manufactures two products15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity
Machining Machine-hours $ 216,700 11,000 MHs
Machine setups Number of setups $ 79,900 170 setups
Production design Number of products $ 81,000 2 products
General factory Direct labor-hours $ 296,400 13,200 DLHs

Activity Measure Product Y Product Z
Machine-hours 6,700 4,300
Number of setups 60 110
Number of products 1 1
Direct labor-hours 7,700 5,500

a.What is the companys plantwide overhead rate? (Round your answer to 2 decimal places.)

Predetermined overhead rate: ______ per DLH

b.Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places and final answers to the nearest dollar amount.)

Manufacturing overhead allocated: Product Y:_______ Product Z: ________

c. What is the activity rate for the Machining activity cost pool? (Round your answer to 2 decimal places.)

Activity rate: ______ per MH

d. What is the activity rate for the Machine Setups activity cost pool?

Activity rate: ______ per setup

e. What is the activity rate for the Product Design activity cost pool?

Activity rate: ______ per product

f. What is the activity rate for the General Factory activity cost pool? (Round your answer to 2 decimal places.)

Activity rate: ______ per DLH

g.Which of the four activities is a batch-level activity?

(a) Machining activity

(b) General factory activity

(c) Product design activity

(d) Machine setups activity

h.Which of the four activities is a product-level activity?

(a) Product design activity

(b) General factory activity

(c) Machining activity

(e) Machine setups activity

i. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? (Do not round intermediate calculations and round your final answer to the nearest dollar amount.)

Total manufacturing overhead cost: ____________

j. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Do not round intermediate calculations and round your final answer to the nearest dollar amount.)

Total manufacturing overhead cost: ____________

k. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your "Percentage" answers to 2 decimal places. (i.e. 0.1234 should be entered as 12.34).)

Manufacturing overhead: Product Y:_______% Product Z: ________%

l. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your "Percentage" answers to 2 decimal places. (i.e. 0.1234 should be entered as 12.34).)

Matching cost: Product Y:_______% Product Z: ________%

m. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your "Percentage" answers to 2 decimal places. (i.e. 0.1234 should be entered as 12.34).)

Machine setups cost: Product Y:_______% Product Z: ________%

n. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y and Product Z? (Round your answers to 2 decimal places.)

Product design cost: Product Y:_______% Product Z: ________%

o. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your "Percentage" answers to 2 decimal places. (i.e. 0.1234 should be entered as 12.34).)

General factory cost: Product Y:_______% Product Z: ________%

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Clinical Audit In Palliative Care

Authors: Irene Higginson

1st Edition

1870905644, 978-1870905640

More Books

Students also viewed these Accounting questions

Question

What is meant by steady state?

Answered: 1 week ago

Question

In what ways can capacity be increased in the short - term?

Answered: 1 week ago