Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below: Standard Quantity

Highland Company produces a lightweight backpack that is popular with college students. Standard variable costs relating to a single backpack are given below:

Standard Quantity or Hours Standard Price or Rate Standard Cost
Direct materials ? $4.5 per yard $?
Direct labor ? ? ?
Variable manufacturing overhead ? $2 per direct labor-hour ?
Total standard cost

$?

Overhead is applied to production on the basis of direct labor-hours. During March, 525 backpacks were manufactured and sold. Selected information relating to the month's production is given below:

Materials Used Direct Labor Variable Manufacturing Overhead
Total standard cost allowed* $9,450 $5,880 $1,470
Actual costs incurred $7,700 ? $1,650
Direct materials price variance ?
Direct materials quantity variance $450 U
Direct labor rate variance ?
Direct labor efficiency variance
Variable overhead rate variance ?
Variable overhead efficiency variance ?
*For the month's production.

The following additional information is available for March's production:

Actual direct labor-hours 900
Standard overhead rate per direct labor-hour $3.9
Standard price of one yard of materials $7.8
Difference between standard and actual cost per backpack produced during March $.20 F
Requirement 1:

a)What is the standard cost of a single backpack? (Round your answer to 2 decimal places. Omit the "$" sign in your response.)

Standard cost for March Production:

Materials ___________

Direct Labor __________

Variable manuf overhead ___________

Total standard cost

Number of backpacks produced __________

Standard cost of a single backpack __________

b)What was the actual cost per backpack produced during March? (Round your answer to 2 decimal places. Omit the "$" sign in your response.)

Standard cost of a single backpack _________

Deduct difference between standard and actual cost _________

Actual cost per backpack _________

c)How many yards of material are required at standard per backpack? (Round your answer to 2 decimal places.)

Total standard cost of materials allowed during March _________

Number of backpacks produced during March _________

Standard materials cost per backpack _________

Standard materials cost per yard _________

Number of yards per backpack _________

d)What was the direct materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values. Omit the "$" sign in your response.)

Materials price variance __________ ___________

Materials quantity variance __________ __________

Spending bariance _________ __________

Requirement 2:

What is the standard direct labor rate per hour? (Round your answer to 2 decimal places. Omit the "$" sign in your response.)

Standard variable manufacturing overhead cost for March ___________

Standard variable manufacturing overhead rate per direct labor-hour ___________

Standard direct labor-hours for March __________

Standard direct labor cost for March __________

Standard direct labor rate per hour ___________

Requirement 3:

What was the direct labor rate variance for March? The direct labor efficiency variance? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values. Omit the "$" sign in your response.)

Labor rate variance ___________ ____________
Labor efficiency variance ___________ ____________

Requirement 4:

What was the variable overhead rate variance for March? The variable overhead efficiency variance?(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values. Omit the "$" sign in your response.)

Variable overhead rate variance ___________ ____________
Variable overhead Efficiency variance ___________ ____________

Requirement 5:

Prepare a standard cost card for one backpack. (Round your answers to 2 decimal places. Omit the "$" sign in your response.)

Standard Quantity or Hours Standard Price or Rate Standard Cost
Direct materials ____________yards 4.5 per yard $__________
Direct labor _____________ours $__ per hour __________
Variable manufacturing overhead ____________hours 2.0 per hour __________
Total standard cost

$_________

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing IT Infrastructures For Compliance

Authors: Robert Johnson, Marty Weiss, Michael G. Solomon

3rd Edition

1284236609, 9781284236606

More Books

Students also viewed these Accounting questions

Question

Explain how to reward individual and team performance.

Answered: 1 week ago