Question
HiTech Products manufactures three types of CD players, Cheap, Econo, and Deluxe. HiTech uses activity-base product costing system. The company has identified five activities and
HiTech Products manufactures three types of CD players, Cheap, Econo, and Deluxe. HiTech uses activity-base product costing system. The company has identified five activities and the related cost drivers for each activity.
Activity Budgeted Costs Cost Driver
Material Handling 225,000 # of Parts
Material Insertion 2,475,000 # of Parts
Automate Machinery 840,000 Machine Hours
Finishing 170,000 Labor Hours
Packaging 170,000 Orders Shipped
Total indirect Manufacturing 3,880,000
costs
Following info pertains to each product line of CD players for next year
Cheap Econo Deluxe
Units to be produced 10,000 5,000 2,000
Orders to be shipped 1,000 500 200
# of parts per unit 10 15 25
Machine hours per unit 1 3 5
Labor hours per unit 2 2 2
- What is HiTechs cost application ate for material handling activity for next year?
- 2.25 per part
- 1.00 per unit
- 6.62 per labor hour
- 13.23 per unit
- What is HiTechs application rate for automated machinery activity for next year?
- 24.00 per machine hour
- 49.42 per unit
- 84.00 per machine hour
- 24.50 per labor hour
- 50.00 per machine hour
- What is HiTechs cost application rate for finishing activity for next year?
- 10.00 per labor hour
- 5.00 per machine hour
- 5.00 per unit
- 5.00 per labor hour
- 7.50 per unit
- Under an activity-based product costing system, what is the per unit cost of Cheap?
- 225.00
- 272.00
- 164.00
- 228.24
- 141.00
Can you explain the calculations to each answer?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started