Hi-Tek Manufacturing, Incorporated, makes two types of industrial component partsthe B300 and the T500. An absorption costing income statement for the most recent period is

Hi-Tek Manufacturing, Incorporated, makes two types of industrial component partsthe B300 and the T500. An absorption costing income statement for the most recent period is shown:

Hi-Tek Manufacturing Incorporated Income Statement
Sales $ 1,689,500
Cost of goods sold 1,252,790
Gross margin 436,710
Selling and administrative expenses 550,000
Net operating loss $ (113,290)

Hi-Tek produced and sold 60,100 units of B300 at a price of $20 per unit and 12,500 units of T500 at a price of $39 per unit. The companys traditional cost system allocates manufacturing overhead to products using a plantwide overhead rate and direct labor dollars as the allocation base. Additional information relating to the companys two product lines is shown below:

B300 T500 Total
Direct materials $ 400,400 $ 162,100 $ 562,500
Direct labor $ 120,800 $ 42,200 163,000
Manufacturing overhead 527,290
Cost of goods sold $ 1,252,790

The company has created an activity-based costing system to evaluate the profitability of its products. Hi-Teks ABC implementation team concluded that $56,000 and $108,000 of the companys advertising expenses could be directly traced to B300 and T500, respectively. The remainder of the selling and administrative expenses was organization-sustaining in nature. The ABC team also distributed the companys manufacturing overhead to four activities as shown below:

Activity Cost Pool (and Activity Measure) Manufacturing Overhead Activity
B300 T500 Total
Machining (machine-hours) $ 211,140 90,700 62,300 153,000
Setups (setup hours) 154,350 73 270 343
Product-sustaining (number of products) 101,000 1 1 2
Other (organization-sustaining costs) 60,800 NA NA NA
Total manufacturing overhead cost $ 527,290

Required:

  1. Compute the product margins for the B300 and T500 under the companys traditional costing system.
  2. Compute the product margins for B300 and T500 under the activity-based costing system.
  3. Prepare a quantitative comparison of the traditional and activity-based cost assignments.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Audit Effectiveness Meeting The IT Challenge

Authors: Kamil Omoteso

1st Edition

1409434680, 978-1409434689

More Books

Students also viewed these Accounting questions