Homework # 4 - COCOMO II You are estimating the effort and schedule needed to implement a new set of microservices in an existing microservice
Homework #COCOMO II
You are estimating the effort and schedule needed to implement a new set of microservices in an
existing microservice system. The estimated size of the new features is KSLOC.
This is a business application that has been in existence in its current form for about four years.
The application is cloudbased, running in an AWS environment. While these enhancements are
considered important, there is no exceptional schedule pressure; features have been prioritized
and are expected to be released in an incremental manner over the course of the project.
The team that built the original system is largely the same team building these enhancements.
They are highly knowledgeable and experienced in this application domain, with this application,
and with these tools. As a team, they can be considered both highly qualified and collaborative.
They are closely colocated, all members being on the same hallway of the same floor of their
facility.
The organization has been assessed as a CMMI maturity level organization.
Use the COCOMO II PostArchitecture Model to estimate the effort and schedule for this project
tables listed as "Boehm, under References The default value for each factor is Nominal.
Show your work; in particular, state briefly why you set each nonnominal factor to the value
that you chose. Explicitly list the category Very Low to Extra High and value eg or
for each scale factor all five and each nonnominal effort multiplier.
Two templates are provided in this assignment. You can use either or create your own in
submitting your homework. Grading Rubric
Getting a "correct" value for PM and TDEV is worth points each, given the values decided
for the scale factors and effort multipliers.
This is basically did you do the arithmetic for the effort and schedule formulas correctly.
Identifying scale factors and effort multipliers correctly, points total.
Not calculating PM is points!
Not calculating TDEV is points!
The object is to estimate effort and schedule!
You can leave out nominal effort multipliers value
Adding nonnominal effort multipliers not in the key
if you included a reasonable rationale, no penalty
if the rationale was inadequate a judgement call for the Grader but not totally
unrealistic, point
if no rationale or a bad rationale was provided, points each
Leaving out a nonnominal effort multiplier in the key, points
not including an effort multiplier implies a value of nominal which would be
incorrect if it should not have been nominal
Providing the "wrong" value for a nonnominal effort multiplier, point each
some judgement is involved in deciding the ordinal value, but the guidance in the
handout as mapped to the assignment should be sufficient
rubric includes variants that the instructor considers a reasonable alternative judgment
Include all five scale factors, even Extra High value
Providing the "wrong" value for a nonnominal scale factor
reasonable rationale in the judgment of the Grader, no penalty
inadequate rationale, point
missing or bad rationale, points
Remember that the nominal value for a scale factor is not or
the Extra High values for scale factors are COCOMO II Factors
Rationale for nonnominal values: COCOMO II Factors
tableEffort MultipliersEMRationale,Category,tableValueRELYDATACPLXRUSEDOCUTIMESTORPVOLACAPPCAPPCONAPEXPLEXLTEXTOOLSITESCEDScaling FactorsSFRationale,Category,ValuePRECFLEXRESLTEAMPMAT
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started