Homework: Homework 6 Save Score: 0.48 of 2 pts 7 of 17 (14 complete) HW Score: 51 33%, 10 27 of 20 pts Problem 14.11 Question Help Given the following product structure, master production schedule, and inventory status below and assuming the requirements for each BOM item is 1(a) develop a gross requirements plan for Item CD) develop a net requirements plan for item Ckck the konto view the product structure, master production schedule and inventory status a) Develop a gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents. Items A and H (Enter your responses as whole numbers) Week 7 3 4 6 1 9 Item 2 8 10 11 100 A 0 60 Gross red Order red 12 170 0 60 0 0 0 0 0 0 0 170 40 0 100 0 BO H 0 0 0 0 0 0 0 Gross red Order reg Grossro Order reg 0 170 30 30 40 100 60 60 170 60 0 0 0 0 0 0 50 100 Enter your answer in the edit fields and then click Check Answer Clear All 6 punts remaininn 101 PM Score: 0.48 of 2 pts 7 of 17 (14 complete) Problem 14.11 0 0 0 0 0 0 0 80 0 40 0 Order req Gross req Order req 80 60 40 170 0 100 60 0 0 0 100 80 40 170 0 0 b) Develop a net requirements plan for item C First find the net requirements plans for its parents: items A and H. Determine the net requirements plan for item A (enter your responses as whole numbers) Level: 0 Item: A Parent: - Lead Time: 1 Quantity: Lot Size: L4L Week 6 7 1 2 3 5 9 10 11 8 100 12 170 60 10 10 10 10 10 10 10 10 Gross requirements Projected on-hand inventory Net requirements Planned order receipts Enter your answer in the edit fields and then click Check Answer 6 parts Clear All remaininn i More Info 8 9 11 Period Gross requirements: A Gross requirements: H 10 60 12 170 100 80 40 Item Lead Time Item Lead Time 2 1 A B D E On Hand 10 90 40 45 80 2 2 F G H J On Hand 85 70 20 90 110 1 1 1 2 2 2 K Print Done More Info E 80 2 K 110 2 A Q H B TI E F E G F G for Print Done Homework: Homework 6 Save Score: 0.48 of 2 pts 7 of 17 (14 complete) HW Score: 51 33%, 10 27 of 20 pts Problem 14.11 Question Help Given the following product structure, master production schedule, and inventory status below and assuming the requirements for each BOM item is 1(a) develop a gross requirements plan for Item CD) develop a net requirements plan for item Ckck the konto view the product structure, master production schedule and inventory status a) Develop a gross requirements plan for Items C. To do so, first find the gross requirements plans for its parents. Items A and H (Enter your responses as whole numbers) Week 7 3 4 6 1 9 Item 2 8 10 11 100 A 0 60 Gross red Order red 12 170 0 60 0 0 0 0 0 0 0 170 40 0 100 0 BO H 0 0 0 0 0 0 0 Gross red Order reg Grossro Order reg 0 170 30 30 40 100 60 60 170 60 0 0 0 0 0 0 50 100 Enter your answer in the edit fields and then click Check Answer Clear All 6 punts remaininn 101 PM Score: 0.48 of 2 pts 7 of 17 (14 complete) Problem 14.11 0 0 0 0 0 0 0 80 0 40 0 Order req Gross req Order req 80 60 40 170 0 100 60 0 0 0 100 80 40 170 0 0 b) Develop a net requirements plan for item C First find the net requirements plans for its parents: items A and H. Determine the net requirements plan for item A (enter your responses as whole numbers) Level: 0 Item: A Parent: - Lead Time: 1 Quantity: Lot Size: L4L Week 6 7 1 2 3 5 9 10 11 8 100 12 170 60 10 10 10 10 10 10 10 10 Gross requirements Projected on-hand inventory Net requirements Planned order receipts Enter your answer in the edit fields and then click Check Answer 6 parts Clear All remaininn i More Info 8 9 11 Period Gross requirements: A Gross requirements: H 10 60 12 170 100 80 40 Item Lead Time Item Lead Time 2 1 A B D E On Hand 10 90 40 45 80 2 2 F G H J On Hand 85 70 20 90 110 1 1 1 2 2 2 K Print Done More Info E 80 2 K 110 2 A Q H B TI E F E G F G for Print Done