Hours Processing Time 3.1 Inspection Time 1.6 Moving Time 4.1 Storing Time 8.7 The Manufacturing Cycle time was: 8.8 hours. 35.7 hours. 17.5 hours. 76.6
Hours | |
Processing Time | 3.1 |
Inspection Time | 1.6 |
Moving Time | 4.1 |
Storing Time | 8.7 |
The Manufacturing Cycle time was:
8.8 hours.
35.7 hours.
17.5 hours.
76.6 hours.
2.
Travis Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below:
Hours | |
Processing Time | 1.9 |
Inspection Time | .9 |
Moving Time | 3.5 |
Storing Time | 9.3 |
The manufacturing cycle efficiency (MCE) was closest to:
0.12.
0.06.
0.68.
0.30.
3.
Tons of metal input | 37,500 | ||
Labor hours | 11,900 | ||
Overhead costs | $ | 134,500 | |
Tons of output produced | 29,500 | ||
The partial productivity for metal is:
0.787.
1.271.
3.151.
0.317.
4.
The Fort Smith Co. has the following information for last year:
Material input | 4,446,000 |
Labor hours | 114,500 |
Yards of output produced | 1,145,000 |
The partial productivity for material is:
0.283.
0.258.
1.026.
3.883.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started