how do i find the standard deviation on a beta districution . The shortest possible duration is 25 days. The longest the project could take

how do i find the standard deviation on a beta districution . The shortest possible duration is 25 days. The longest the project could take is 65 days. The most likely duration is 50 days.d. We can be 95.44% sure that the project duration will fall between what two values? (48 days & 7 days)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Welcome To Management

Authors: Ryan Hawk, General Stanley McChrystal

1st Edition

1260458059, 978-1260458053

More Books

Students also viewed these General Management questions

Question

Explain why you agree or disagree with this statement.

Answered: 1 week ago