Question
1 Approved Answer
How do you find earned value if you do not know the percentage of work performed? Activity Start Planned Duration Actual Duration Plan Date Actual
How do you find earned value if you do not know the percentage of work performed?
Activity | Start | Planned Duration | Actual Duration | Plan Date | Actual Date | Difference | Budget | Actual | Difference | Resource |
Call Center Stations | ||||||||||
Call center stations inventory | 3/1/2020 | 14 | 14 | 3/15/2020 | 3/15/2020 | 0 | $2,100.00 | $2,100.00 | $0.00 | OC1 |
Call center layout-new | 3/15/2020 | 15 | 18 | 3/30/2020 | 4/2/2020 | 3 | $ 4,500.00 | $ 5,400.00 | $900.00 | C1,C2,C3 |
Call center stations breakdown | 4/2/2020 | 8 | 13 | 4/10/2020 | 4/15/2020 | 5 | $ 2,400.00 | $ 3,900.00 | $1,500.00 | C1,C2,C3 |
Call center stations pack | 4/10/2020 | 5 | 20 | 4/15/2020 | 4/30/2020 | 15 | $ 1,500.00 | $ 6,000.00 | $4,500.00 | C1,C2,C3 |
Call center stations move | 4/30/2020 | 10 | 10 | 4/20/2020 | 5/10/2020 | 20 | $ 2,000.00 | $ 2,000.00 | $0.00 | C1,C2,C3 |
Call center stations install | 5/10/2020 | 9 | 15 | 5/1/2020 | 5/25/2020 | 24 | $1,800.00 | $3,000.00 | $1,200.00 | C4,C5 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
In Earned Value Management EVM the earned value represents the value of work that has been completed ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started