Question: How long is this project expected to last? Calculate the earliest start/earliest finish, latest start/latest finish , and slack for each activity. Indicate them in
How long is this project expected to last?
Calculate the earliest start/earliest finish, latest start/latest finish, and slack for each activity. Indicate them in a form of a network diagram
The activity times are as follows: Activity Activity Time (weeks) A 7 B C D E F G H 9 6 13 12 3 5 10
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
To determine the project duration we need to analyze the network diagram and identify the critical path which consists of the activities with zero sla... View full answer