How many days will the project take? ID Description Predecessor Time A Survey site None 2 B Excavate site A 4 C Install power lines
How many days will the project take? ID Description Predecessor Time A Survey site None 2 B Excavate site A 4 C Install power lines B 3 D Install drainage B 5 E Pour foundation C, D 3 Group of answer choices 14 days 11 days 12 days