Question

1 Approved Answer

How to arrive at response? Undersea Construction Ltd commenced the construction of a tunnel under a major river for public transport on 1 July 20X4.

image text in transcribedimage text in transcribed

How to arrive at response?

Undersea Construction Ltd commenced the construction of a tunnel under a major river for public transport on 1 July 20X4. It has a fixed-price contract for total revenues of $36 million. The expected completion date is 30 June 20x7. The expected total cost to Undersea Construction at the beginning of the project is $27 million. The following information relates only to the construction of the tunnel: 20X5 20X6 20X7 For the year ending 30 June $'000 $'000 $'000 Costs for the year 5,000 15,000 10,000 Costs incurred to date 5,000 20,000 30,000 Estimated costs to complete 22,000 8,500 Progress billings during the 10,000 22,000 4,000 year Cash collected during the year 9,000 19,000 8,000 Undersea Construction uses the percentage of completion method based on cost to account for its construction contracts. All cost estimates are reliable. 10. If in 20X6, the estimated costs to complete are $18,000 (not $8,500) and the $18,000 cost is indeed incurred in 20X6, the gross profit or loss reported each year by Undersea Construction on this construct will be: (in $'000s) 20X5 2086 20X7 a) $3,596 $2,000 (loss) $8.000 b) $1,667 $2,000 (loss) Szero C) $3,576 $5,833 Szero d) $1,667 $3,867 (loss) $zero e) $1,667 $3,867 (loss) $4,000 Undersea Construction Ltd commenced the construction of a tunnel under a major river for public transport on 1 July 20X4. It has a fixed-price contract for total revenues of $36 million. The expected completion date is 30 June 20x7. The expected total cost to Undersea Construction at the beginning of the project is $27 million. The following information relates only to the construction of the tunnel: 20X5 20X6 20X7 For the year ending 30 June $'000 $'000 $'000 Costs for the year 5,000 15,000 10,000 Costs incurred to date 5,000 20,000 30,000 Estimated costs to complete 22,000 8,500 Progress billings during the 10,000 22,000 4,000 year Cash collected during the year 9,000 19,000 8,000 Undersea Construction uses the percentage of completion method based on cost to account for its construction contracts. All cost estimates are reliable. 10. If in 20X6, the estimated costs to complete are $18,000 (not $8,500) and the $18,000 cost is indeed incurred in 20X6, the gross profit or loss reported each year by Undersea Construction on this construct will be: (in $'000s) 20X5 2086 20X7 a) $3,596 $2,000 (loss) $8.000 b) $1,667 $2,000 (loss) Szero C) $3,576 $5,833 Szero d) $1,667 $3,867 (loss) $zero e) $1,667 $3,867 (loss) $4,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting An IFRS Standards Approach

Authors: Pearl Tan, Chu Yeong Lim, Ee Wen Kuah

4th Edition

9789814821278, 9814821276

More Books

Students also viewed these Accounting questions

Question

How would you train others to perform the task? Explain.

Answered: 1 week ago

Question

Why is it important for a firm to conduct career development?

Answered: 1 week ago