Question

1 Approved Answer

How to complete this Planned Value (PV) and Earned Value (EV) at the status date Schedule Variance (SV) and Schedule Performance Index (SPI) at the

How to complete this

Planned Value (PV) and Earned Value (EV) at the status date

Schedule Variance (SV) and Schedule Performance Index (SPI) at the status date

Cost Variance (CV) and Cost Performance Index (CPI) at the status date

Estimated duration of the project assuming the future schedule performance will be influenced by the past Schedule Performance Index.

Estimated cost at project completion assuming the future cost performance will be influenced past Cost Performance Index only.

Present the above calculated results in tabular format. Make sure to include the table number (i.e., Table xx, where xx is the table number) and an appropriate title for the table. All the columns of the table must have appropriate column heading. The column heading must include relevant unit.

Present the following quantities in a single plot. The plot must include a figure number (i.e., Figure xx, where xx is the Figure number) and an appropriate caption.

Schedule Variance (SV) at the status date

Cost Variance (CV) at the status date

Time Variance (TV) at the status date

Cost at completion

Cost Variance (CV) at completion

Delay at Completion (DAC)

image text in transcribed

It was decided to budget the project using normal duration of each of the activities. The progress of the project activities exactly at the middle of the planned project duration are given below: It was decided to budget the project using normal duration of each of the activities. The progress of the project activities exactly at the middle of the planned project duration are given below

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

2001 Miller Local Government Audits

Authors: Rhett D. Harrell

1st Edition

015607219X, 978-0156072199

More Books

Students also viewed these Accounting questions