How to complete this Planned Value (PV) and Earned Value (EV) at the status date Schedule Variance (SV) and Schedule Performance Index (SPI) at the
How to complete this
Planned Value (PV) and Earned Value (EV) at the status date
Schedule Variance (SV) and Schedule Performance Index (SPI) at the status date
Cost Variance (CV) and Cost Performance Index (CPI) at the status date
Estimated duration of the project assuming the future schedule performance will be influenced by the past Schedule Performance Index.
Estimated cost at project completion assuming the future cost performance will be influenced past Cost Performance Index only.
Present the above calculated results in tabular format. Make sure to include the table number (i.e., Table xx, where xx is the table number) and an appropriate title for the table. All the columns of the table must have appropriate column heading. The column heading must include relevant unit.
Present the following quantities in a single plot. The plot must include a figure number (i.e., Figure xx, where xx is the Figure number) and an appropriate caption.
Schedule Variance (SV) at the status date
Cost Variance (CV) at the status date
Time Variance (TV) at the status date
Cost at completion
Cost Variance (CV) at completion
Delay at Completion (DAC)
It was decided to budget the project using normal duration of each of the activities. The progress of the project activities exactly at the middle of the planned project duration are given below: It was decided to budget the project using normal duration of each of the activities. The progress of the project activities exactly at the middle of the planned project duration are given belowStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started