Question
HQ Ltd commences construction of an office building on 1 January 2018 for JX Ltd. The construction contract is considered to represent one performance obligation
HQ Ltd commences construction of an office building on 1 January 2018 for JX Ltd. The construction contract is considered to represent one performance obligation and will be the unit of account for contract accounting. It signs a fixed price contract for total revenue of $20 million. The project is expected to be completed by 31 December 2020. The expected total cost as estimated at the commencement of construction is $16 million. The expected cost to complete the construction project can change throughout the project (in this case it does). The following information relates to the project:
| 2018 ($000) | 2019 ($000) | 2020 ($000) |
Costs for the year | 8000 | 5000 | 4500 |
Costs incurred to date | 6000 | 11500 | 17500 |
Estimated costs to complete | 11500 | 6000 | - |
Progress billings during the year | 8500 | 4500 | 7000 |
Cash collected during the year | 7500 | 6500 | 6000 |
Required:
a) Calculate the income recognized each year using percentage completion method. (Show all workings) (3 marks)
b) Provide the journal entries for the year 2018, assuming that stage of completion and the outcome of the construction contract can be reliably estimated. (7 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started