https://www.coursehero.com/load_question_attachment.php?q_att_id=3375803&thread_id=38812458 Question 2 The following data for Kitchen Tile Company relates to the production of 18 000
Fantastic news! We've Found the answer you've been seeking!
Question:
https://www.coursehero.com/load_question_attachment.php?q_att_id=3375803&thread_id=38812458
Question 2 The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates xed overhead costs at a standard rate of $19 per direct
labour hour. Direct labour:
Standard cost is 5 tiles per hour at $24 per hour
Actual cost per hour was $24.50
Labour efficiency variance was $6 720 F
Fixed overhead costs:
Estimated: $60 000
Actual: $58 720 Required
(a) How many actual labour hours were worked to produce the 18 000 tiles?
(b) What is the price variance for direct labour? (c) What is the budget variance for xed costs?
Posted Date: