Hypothetical Project: Developing a website for a French restaurant called Crepes & Co. Develop a roadmap and release plan using Scrum/Agile principles, practices, and philosophies.

Hypothetical Project: Developing a website for a French restaurant called Crepes & Co. Develop a roadmap and release plan using Scrum/Agile principles, practices, and philosophies. This assignment has two deliverables: 1) an Excel spreadsheet (Product Backlog Template) to detail your roadmap/release plan and 2) a paper describing the concepts. The paper should include the following: 1. Vision statement * What is a vision statement? * Product/project vision statement 2. Product backlog * What is a Product Backlog? * Describe high-level functionality * Provide a Story Map 3. Release plan * What is a Release Plan? * Fixed scope or fixed date * Sprints per release, story points per sprint, etc. * Layout calendar-based release schedule 4. Effort needed * Describe what kind of roles are needed, availability, etc. * Determine costs 5. Scheduling and monitoring planSUGGESTED STEPS 1. Story map the project 2. Enter Epics and User stories into the Agile Roadmap Template 3. Assign story points to your user stories (using Fibonacci scale. 4. Assign Business Value and Risk to calculate the ValueRisk score. Sort the template by Value Risk Score, giving you a prioritized Product Backlog. 5. Estimate the velocity (story points per sprint) and sprints per release. 6. Layout sprints (may have to play with story points)7. Layout releases 8. Write paperText: Rubin, K. (2013). Essential Scrum: A practical guide to the most popular agile processPlease use in text citations and give references from the book and PMI See attached for template

image text in transcribed
Business Risk Impact of not Value Score implementing: 10 Insignificant = no harm Critical Story 2 Significant = tangible harm Value, Risk Score 7 3 Damaging = to reputation Themes: Feature/Functionality points Projected Sprint Release # value times risk Notes Line Ref # | Epic # Epic High or confidence allocated 4 Serious = large impact 4 Medium service compromise 5 Grave = Complete Low Compromise) 0 . . . . . . . . . . . . = * Cost per point is $1165 (based on cost per sprint of $69,880 divided by 60 points per sprint)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David Kroenke

2nd Edition

0136078680, 9780136078685

More Books

Students also viewed these General Management questions

Question

3. To retrieve information from memory.

Answered: 1 week ago

Question

2. Value-oriented information and

Answered: 1 week ago

Question

1. Empirical or factual information,

Answered: 1 week ago