I am about 75% through this diagram, and I want to make sure I am on the right track. Draw an AOA diagram, either by
I am about 75% through this diagram, and I want to make sure I am on the right track.
Draw an AOA diagram, either by hand or in Lucidchart or Microsoft Visio. Also, Indicate the ET (Earliest Time) and LT (Latest Time) times for each of the activities A through G? And finally, what are the slacks for each of the activities A through G?
Activity | Predecessor | Duration in Months |
Start | 0 | |
A | Start | 6 |
B | A, E | 2 |
C | B | 2 |
D | C | 3 |
E | Start | 1 |
F | A, E | 1 |
G | B, F | 7 |
Finish | D, G | 0 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started