Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

I am having difficulty with trying to complete these problems which are in the empty fields. In order to complete the questions, an excel spreadsheet

I am having difficulty with trying to complete these problems which are in the empty fields. In order to complete the questions, an excel spreadsheet has to be used as formulas are necessary to complete the problems. I have included screenshots of the full spreadsheet. This assignment requires the blank fields to be completed. The areas that are shaded in green is where the answers would populate but I need help with knowing how to calculate the metrics properly. Please help!

image text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribedimage text in transcribed
20% 20% #N/A #N/A % Deviation Number of units sold % Deviation Number of units sold from Base NPV from Base NPV Base Case 900 Base Case 900 #N/A -20% -20% #N/A #N/A -10% -10% #N/A #N/A 0% 0% #N/A #N/A 10% 10% #N/A #N/A 20% 20% #N/A #N/A Constructing the project's sensitivity graph % Deviation NPV with Variables at Different Deviations from Base from Sales Price Variable Cost per Number of Units Base Case Unit Sold 20% $0 10% $0 0% $8886 $0 10% $0 20% $o c. Conducting a scenario analysis Unit Sales Price, Variable Cost Scenari Probability Sales Year 1 per Unit, Year 1 NPV Formulas Best Case 30% $0 $0 #N/A Base Case 40% $0 $0 #N/A Worst Case 30% $0 #N/A Expected NPV #N/A Standard Deviation #N/A Coefficient of Variation #N/A Page 2d. If the project appears to be more or less risky than an average project, finding its risk-adjusted NPV, IRR, and payback CV range of firm's average-risk project: 0.7 to 1.3 Low-risk WACC 9% WACC 12% High-risk WACC 15% Risk-adjusted WACC #N/A Risk-adjusted NPV #N/A Risk-adjusted IRR #N/A Risk-adjusted regular payback period (years) #N/A Page 3ssues in Capital Budgeting a. Developing a spreadsheet model, and using it to find the project's NPV, IRR, and payback Equipment cost, Year 0 $13,000,000 Net working capital as % of next year's sales 9% Units sold per year 900 Sales price per unit, Year 1 $25,500 Variable cost per unit (excl. depr.), Year 1 $17,500 Nonvariable costs (excl. depr.), Year 1 $2,000,000 Inflation rate in sales price and costs 4% Market value of equipment, Year 4 $600,000 Tax rate 25% WACC 12% Years Intermediate Calculations 0 3 Unit sales Sales price per unit Variable cost per unit (excl. depr.) Nonvariable costs (excl. depr.) Sales revenues Required level of net working capital Basis for depreciation Annual depreciation rate (MACRS) 20.00% 32.00% 19.20% 11.52% Annual depreciation expense Ending book value Salvage value Profit (or loss) on sale of equipment Tax on profit (or loss) due to sale of equipment Net cash flow due to sale of equipment Years Cash Flow Forecast Sales revenue Variable costs (excl. depr.) Nonvariable costs (excl. depr.) Depreciation Operating income before taxes Taxes on operating income Net operating profit after taxes Add back depreciation Equipment purchases Cash flow due to change in NWC Net cash flow due to sale of equipment Project's net cash flows NPV #N/A IRR #N/A Years Net cash flow Cumulative net cash flow Part of year required for payback Regular payback period (years) #N/A b. Conducting a sensitivity analysis to determine the sensitivity of NPV to changes in the sales price, variable costs per unit, and number of units sold % Deviation Sales price, Year 1 % Deviation Sales price, Year 1 from Base NPV from Base NPV Base Case $25,500 Base Case $25,500 #NIA -20% -20% #N/A #N/A -10% 10% #N/A #N/A 0% 0% #N/A #N/A 10% 10% #N/A #N/A 20% 20% #N/A #N/A % Deviation Variable costs per unit, Year 1 % Deviation Variable costs per unit, Year from Base NPV from Base NPV Base Case $17,500 Base Case $17,500 #N/A -20% -20% #N/A #N/A -10% -10% #N/A #N/A 0% 0% #N/A #N/A 10% 10% #N/A #N/A Page 1Start with the partial model in the file Ch13 P18 Build a Model.x/sx. Webmasters.com has developed a powerful new server that would be used for corporations' Internet activities. It would cost $13 million at Year 0 to buy the equipment necessary to manufacture the server. The project would require net working capital at the beginning of each year in an amount equal to 9% of the year's projected sales; for example, NWCo = 9%(Sales,). The servers would sell for $25,500 per unit, and Webmasters believes that variable costs would amount to $17,500 per unit. After Year 1, the sales price and variable costs will increase at the inflation rate of 4%. The company's nonvariable costs would be $2 million at Year 1 and would increase with inflation. The server project would have a life of 4 years. If the project is undertaken, it must be continued for the entire 4 years. Also, the project's returns are expected to be highly correlated with returns on the firm's other assets. The firm believes it could sell 900 units per year. The equipment would be depreciated over a 5-year period, using MACRS rates. The estimated market value of the equipment at the end of the project's 4-year life is $600,000. Webmasters.com's federal-plus-state tax rate is 25%. Its cost of capital is 12% for average-risk projects, defined as projects with a coefficient of variation of NPV between 0.7 and 1.3. Low-risk projects are evaluated with a 9% project cost of capital and high-risk projects at 15%. The data has been collected in the Microsoft Excel file below. Download the spreadsheet and perform the required analysis to answer the questions below. Do not round intermediate calculations.a. Develop a spreadsheet model, and use it to find the project's NPV, IRR, and payback. Round your answer for the NPV to the nearest dollar and for the IRR and payback to two decimal places. NPV IRR Regular payback period years b. Now conduct a sensitivity analysis to determine the sensitivity of NPV to changes in the sales price, variable costs per unit, and number of units sold. Set these variables' values at 10% and 20% above and below their base-case values. Round your answers to the nearest dollar. Use a minus sign to enter a negative value, if any. % Deviation from NPV with Variables at Different Deviations from Base Base Case Sales Price Variable Cost per Unit Number of Units Sold -20% -10% 0% 10% 20% $ $c. Now conduct a scenario analysis. Assume that there is a 30% probability that best-case conditions, with each of the variables discussed in Part b being 20% better than its base-case value, will occur. There is a 30% probability of worst-case conditions, with the variables 20% worse than base, and a 40% probability of base-case conditions. Round your answers for the NPV and standard deviation to the nearest dollar and for the coefficient of variation to two decimal places. Use a minus sign to enter a negative value, if any. Scenario NPV Best Case in Base Case Worst Case $ Expected NPV Standard Deviation Coefficient of Variation d. If the project appears to be more or less risky than an average project, find its risk-adjusted NPV, IRR, and payback. Round your answer for the NPV to the nearest dollar and for the IRR and payback to two decimal places. Use a minus sign to enter a negative value, if any. Risk-adjusted NPV $ Risk-adjusted IRR % Risk-adjusted regular payback period years

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting

Authors: kieso, weygandt and warfield.

IFRS Edition

978-1118443965, 1118800532, 9781118800539, 978-0470873991

More Books

Students also viewed these Accounting questions

Question

Classes cannot:

Answered: 1 week ago