I am struggling with CPIF fee calculations. The problem goes as follows: -Given: a Cost Plus Incentive Fee (CPIF) project you are managing- The numbers
I am struggling with CPIF fee calculations. The problem goes as follows:
-Given: a Cost Plus Incentive Fee (CPIF) project you are managing-
The numbers ->Target cost: $100,000Actual cost: $80,000Target fee: $20,000
Maximum fee: $25,000Minimum fee: $15,000Sharing ratio: 60/40
My Work:20,000 x.04 = 8,000
Target Cost - Actual Cost= $20,000 x .04 (40%)= $8,000
$80000+ $20000+$8000 = $108,000 Total price
Actual Cost+ Target Fee + Contractor share
Question: 1.How much fee would the contractor earn? 28,000 (IS THIS RIGHT and why is it over the max fee?)
2.What should be the final price of the contract? $108,000 (Is this right? )
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started