I have a process making pizzas Task Predecessor Time (Seconds) A None 45 B None 30 C A, B 45 D B 20 E C
I have a process making pizzas Task Predecessor Time (Seconds) A None 45 B None 30 C A, B 45 D B 20 E C 10 F D, E 24 GE 40 If my desired output rate is 75 pizzas per hour, what is the efficiency of my setup? Answer in the nearest percentage and answer without the percent sign (e.g., 33.4% becomes 33)