Question: I have completed making the plan but need help answering the following questions Microsoft Project Schedule 2 Create a schedule using Microsoft Project and answer

 I have completed making the plan but need help answering the
following questions Microsoft Project Schedule 2 Create a schedule using Microsoft Project
and answer the questions provided in the exam. Create a schedule using
the list of activities below with a start date of October 3,
2016 and including key California state holidays Duration Predecessors Notes Task DescriptionI have completed making the plan but need help answering the following questions

Microsoft Project Schedule 2 Create a schedule using Microsoft Project and answer the questions provided in the exam. Create a schedule using the list of activities below with a start date of October 3, 2016 and including key California state holidays Duration Predecessors Notes Task Description |Notice to Proceed ID 0 days 5 days 3 Remove existing pavement 6 days | 2 Mobilization 4 Remove existing concrete 5 34 Demolition Remove existing subgrade 6 Replace unsuitable base 3 days 8 days new subgrade 4 days 8 Install new curb and guter6 days 7 days 2 days 3 days 2 days 3 days 3 days 0 days Reconstruction 10 install new traffic signais Reconstruction 11 Install new signage 12 13 14 15 Project Completion 12 13 14 . Navigate to the "Resource Sheet and add the following resources o Create the following work resources: i. Excavator@$129hr (Std.) ii. Grader@$103hr (Std.) ili. Scraper$115/hr (Std.) iv. Bulldozer@$83/hr (Std.) MacBook Pro a Search SafeFinder

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!