i need C the standard time A job was timed for 60 cycles and had an average of 119 minutes per piece. The performance rating

i need C the standard time image text in transcribed
image text in transcribed
A job was timed for 60 cycles and had an average of 119 minutes per piece. The performance rating was 89 percent, and workday allowances are 14 percent. Determine each of the following a. Observed time (Round your onswer to 2 decimal ploces.) Answer is complete and correct. b. Normal time (Round your onswer to 2 decimal places.) b. Normal time. (Round your answer to 2 decimal places.) Answer is complete and correct. 1.06minutes c. Standard time. (Round your onswer to 2 decimol places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Systems Management

Authors: Barbara McNurlin

8th Edition

0132437155, 9780132437158

More Books

Students also viewed these General Management questions

Question

True or False The keys in a dictionary must be mutable objects.

Answered: 1 week ago

Question

What are the assumptions required of a multiple regression model?

Answered: 1 week ago

Question

2. Information that comes most readily to mind (availability).

Answered: 1 week ago

Question

3. An initial value (anchoring).

Answered: 1 week ago

Question

4. Similarity (representativeness).

Answered: 1 week ago