I need help finding part e please This exercise contains only parts a,b,c,d, and e. a) Based on the activity time estimates, the expected times
I need help finding part e please
This exercise contains only parts a,b,c,d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): b) The expected completion time of the critical path =20.17 weeks (round your response to two decimal places). The expected completion time of the path other than the critical path = weeks (round your response to two decimal places). c) The variance of the critical path = weeks (round your response to two decimal places). The variance of the path other than the critical path = weeks (round your response to two decimal places). d) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 23 weeks or less = (enter as a probability and round your response to two decimal places). e) If the time to complete the activities on the non critical path is normally distributed, then the probability that the non critical path will be finished in 23 weeks or less = (enter as a probability and round your response to two decimal places). Get more helpStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started