I need help with this and please list step by step: Consider the following table: ACTIVITYPREC. ACT.TIMEESTIMATES(days) t o t ml t p t e

I need help with this and please list step by step:

Consider the following table:

ACTIVITYPREC. ACT.TIMEESTIMATES(days)

totmltpte

A---444

BA456

CA246

DB468

EC135

FD153

GF, E333

1) Construct a PERT network.

[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.

3) Find the completion time and the standard deviation () for the project round off the standard

deviation to the nearest hundredth:twodecimal places.

4) What is the completion time at 95%confidence level?

5) What is the likelihood of this project being completed earlier than19days?

6) What is the likelihood of this project being completed later than23days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Horngrens Cost Accounting A Managerial Emphasis

Authors: Srikant M. Datar, Madhav V. Rajan

17th Edition

0135628474, 9780135628478

More Books

Students also viewed these Accounting questions