Question
I need help with this and please list step by step: Consider the following table: ACTIVITYPREC. ACT.TIMEESTIMATES(days) t o t ml t p t e
I need help with this and please list step by step:
Consider the following table:
ACTIVITYPREC. ACT.TIMEESTIMATES(days)
totmltpte
A---444
BA456
CA246
DB468
EC135
FD153
GF, E333
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
3) Find the completion time and the standard deviation () for the project round off the standard
deviation to the nearest hundredth:twodecimal places.
4) What is the completion time at 95%confidence level?
5) What is the likelihood of this project being completed earlier than19days?
6) What is the likelihood of this project being completed later than23days?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started