Question
I need help with this........ You are in charge of a project. Your team has determined that there are 7 activities to be completed. Here
I need help with this........
You are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track?
Activity | Time | Immediate Predecessor |
---|---|---|
A | 10 Weeks | None |
B | 6 Weeks | A |
C | 7 Weeks | A |
D | 6 Weeks | B |
E | 8 Weeks | C |
F | 3 Weeks | D |
G | 4 Weeks | F |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started