I need someone to help mebuild thisMicrosoft project assignment and give me the actual file, not a word doc or PDF. 22. The CyClon project
I need someone to help mebuild thisMicrosoft project assignment and give me the actual file, not a word doc or PDF.
22. The CyClon project team has started gathering information necessary to develop
a project network-predecessor activities and activity time in days. The
results of their meeting are found in the following table:
Activity Description Duration Predecessor
1 CyClon Project
2 Design 10
3 Procure prototype parts 10 2
4 Fabricate parts 8 2
5 Assemble prototype 4 3, 4
6 Laboratory test 7 5
7 Field test 10 6
8 Adjust design 6 7
9 Order stock components 10 8
10 Order custom components 15 8
11 Assemble test production unit 10 9, 10
12 Test unit 5 11
13 Document results 3 12
Part A. Create a network based on the above information. How long will the project
take? What is the critical path?
Part B. Upon further review the team recognizes that they missed three finish-tostart
lags. Procure prototype parts will involve only 2 days of work but it will take
8 days for the parts to be delivered. Likewise, Order stock components will take
2 days of work and 8 days for delivery and Order custom components 2 days of
work and 13 days for delivery.
Reconfigure the CyClon schedule by entering the three finish-to-start lags.
What impact did these lags have on the original schedule? On the amount of work
required to complete the project?
Part C. Management is still not happy with the schedule and wants the project
completed as soon as possible. Unfortunately, they are not willing to approve additional
resources. One team member pointed out that the network contained only
finish-to-start relationships and that it might be possible to reduce project duration
by creating start-to-start lags. After much deliberation the team concluded
that the following relationships could be converted into start-to-start lags:
Procure prototype parts could start 6 days after the start of Design.
Fabricate parts could start 9 days after the start of Design.
Laboratory test could begin 1 day after the start of Assemble prototype.
Field test could start 5 days after the start of Laboratory test.
Adjust design could begin 7 days after the start of Field test.
Order stock and Order custom components could begin 5 days after Adjust
design.
Test unit could begin 9 days after the start of Assemble test production unit.
Document results could start 3 days after the start of Test unit.
Reconfigure the CyClon schedule by entering all nine start-to-start lags. What
impact did these lags have on the original schedule (Part A)? How long will the
project take? Is there a change in the critical path? Is there a change in the sensitivity
of the network? Why would management like this solution?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started